NEW QUESTION # 23
You are planning an SAP S/4HANA conversion.
Which conversion-specific tasks must be performed during the preparation phase?
- A. Run the database migration to the SAP HANA database.
- B. Check the compatibility of custom code with SAP S/4HANA.
- C. Perform the migration of data to the new data structure.
- D. Solve problems from the simplification item (SI) checks.
Answer: B
NEW QUESTION # 24
What SAP systems can you use for the ABAP Test Cockpit (ATC) to perform the custom code analysis for an SAP S/4HANA conversion? Note: There are 2 correct answers to this question.
- A. SAP Solution Manager 7.2
- B. SAP S/4HANA Server 2022
- C. SAP ECC system from SAP ERP 6.0 EHP 8
- D. Standalone AS ABAP with SAP BASIS 752
Answer: B,D
NEW QUESTION # 25
You are running an SAP ECC system with SAP BASIS 740, non-Unicode on SAP MaxDB. Which of the following are possible paths to perform an SAP S/4HANA conversion? Note: There are 3 correct answers to this question.
- A.
- B.
- C.
- D.
- E.
Answer: C,D,E
NEW QUESTION # 26
You are performing an SAP S/4HAN A conversion with DMO. You are using the downtime-optimized data conversion (DoC).
Which steps can partially be moved to uptime processing? Note: There are 2 correct answers to this question.
- A. Main import
- B. Software update
- C. Migration
- D. Conversion
Answer: C,D
NEW QUESTION # 27
You are performing an SAP S/4HANA conversion for your production system. This conversion project requires that certain business functions are switched on. Following SAP recommendations, how will you achieve this? Note: There are 2 correct answers to this question.
- A. Activate the required business functions in the switch framework from section S/4H_ALWAYS_ON_FUNCTIONS.
- B. Import a transport request from the development system that contains the recording of the activation.
- C. During conversion, SUM delivers some business functions already activated.
- D. Activate the required business functions manually in the production system.
Answer: B,C
NEW QUESTION # 28
Which preoperational steps must be performed for an SAP S/4HANA conversion? Note: There are 2 correct answers to this question.
- A. Perform the custom code adjustment.
- B. Delete client 066 (Early-Watch client).
- C. Uninstall SAP Fiori apps NO T released for SAP_UI 7.50.
- D. Install add-on SAP Gateway 7.50.
Answer: B,C
NEW QUESTION # 29
You are executing as SAP S/4HANA Conversion with scenario strategy Standard. When will the shadow instance be stopped for thee last time?
- A. As part of the cleanup process
- B. At the end of the downtime
- C. Early in the downtime
- D. Before the downtime starts
Answer: D
NEW QUESTION # 30
When using the DMO of SUM, which files can be handled by SUM in the download directory? Note:
There are 2 correct answers to this question.
- A. Parameter file SAPup_add.par
- B. Breakpoint configuration file SAPUPPHAS.BRK
- C. MIGRATE_DT_DUR.XML file from a previous run
- D. Stack XML file calculated by the maintenance planner
Answer: C,D
NEW QUESTION # 31
What are the benefits of using the benchmarking option of the DMO for SUM? Note: There are 2 correct answers to this question.
- A. You can find the optimal number of parallel R3load processes by monitoring host performance.
- B. You can record the modification adjustment during migration and use the transports in the next runs.
- C. You can obtain migration duration files from a previous benchmark run that can be used to optimize the next runs.
- D. You can verify that the content of the download directory matches the stack XMML file.
Answer: A,C
NEW QUESTION # 32
What is the name of the additional server that is used for a transition to SAP S/4HANA Cloud Private Edition?
- A. Central Instance
- B. Migration Server
- C. Migration Hub
- D. Transition Server
Answer: B
NEW QUESTION # 33
What is the minimum SAP BASIS release of an SAP ECC system that can be converted t o an SAP S/4HANA Server 2023?
- A. 0
- B. 1
- C. 2
- D. 3
Answer: C
NEW QUESTION # 34
During the upgrade of your development system, you run into the adjustment of non-dictionary objects, handled by transaction SPAAU. There you find programs that are shown in status "automatic adjustment" (green traffic light).
What will happen with these programs when you continue with your upgrade without performing any other actions inside your SAP system?
- A. Before continuing with the next phase, SUM asks for a modification adjustment transport.
- B. SUM refuses to continue unless you have marked a transport request as modification adjustment transport.
- C. SUM continues with the next phase and your modifications are kept as in the start release.
- D. SUM continues with the next phase, and the coding of your modified objects are set to the new SAP standard.
Answer: A
NEW QUESTION # 35
Which of the following SUM activities require a stack XML file calculated by the maintenance planner? Note: There are 3 correct answers to this question.
- A. SAP S/4HANA conversion including DMO
- B. SAP S/4HANA conversion without DMO
- C. DMO without system update
- D. Prerequisite check
- E. Benchmark tool
Answer: A,B,D
NEW QUESTION # 36
You are performing an SAP S/4HANA conversion.
When does the silent data migration (SDM) take place using the SUM defaults?
- A. During the Preprocessing roadmap step
- B. During the Post processing roadmap step
- C. Before the start of the SUM technical downtime
- D. After SUM has ended
Answer: D
NEW QUESTION # 37
Which step can be optimized when you provide the MIGRATE_DT_DURXML file to SUMM?
- A. Silent data migration (SDM)
- B. Downtime conversion
- C. Downtime migration
- D. Shadow on target creation
Answer: C
NEW QUESTION # 38
Which of the following are valid options to check the progress of an in place SUM DMO run? Note:
There are 2 correct answers to this question.
- A. Check the dump size of the database export in the SUM directory, subdirectory a bap, subdirectory load.
- B. Check the Charts Control Center in the SUM UL
- C. Check the log files written in the SUM directory, subdirectory a bap, subdirectory log
- D. Check logs for jobs starting with RSUPG SGEN in the SAP system.
Answer: B,C