NEW QUESTION 23
Where should a team manager look for information about the quality required for a product?
- A. Team plan
- B. Quality management approach
- C. Product description
- D. Project initiation documentation
Answer: C
Explanation:
Section: Volume B
Explanation/Reference: http://prince2.wiki/Quality#The_Quality_Knowledge_provided_by_PRINCE2
NEW QUESTION 24
Which process provides the Project Board with sufficient information for it to review the success of a completed stage and confirm continued business justification?
- A. Managing a Stage Boundary
- B. Directing a Project
- C. Closing a Project
- D. Controlling a Stage
Answer: A
NEW QUESTION 25
Where can people who join a project after initiation quickly and easily find information about how the project is being managed?
- A. Project brief
- B. Project product description
- C. Project initiation documentation
- D. Project mandate
Answer: C
NEW QUESTION 26
What do acceptance criteria identify?
- A. A measureable improvement resulting from a project outcome
- B. The approach that will be used to prove whether the project's products have been completed
- C. The measureable definitions of the attributes for a set of products to be acceptable to key stakeholders
- D. The project controls set up during the process Initiating a Project
Answer: C
NEW QUESTION 27
Which is an objective of the Closing a Project process?
- A. Prepare the plan for the next stage
- B. Produce a Benefits Review Plan to identify what benefits are expected
- C. Check that all benefits are realized before closing a project
- D. Assess any benefits that have already been realized
Answer: D
NEW QUESTION 28
Which is one of the six aspects of project performance to be managed?
- A. Timescales
- B. Work
- C. Estimate
- D. Efficiency
Answer: A
Explanation:
Section: Volume B
Explanation/Reference: http://prince2.wiki/
Introduction:_The_PRINCE2_Foundation_Training_Manual#Six_variables_.2F_six_performance_targets
NEW QUESTION 29
How is a Benefits Review Plan used in the Closing a Project process?
- A. To capture side-effects (beneficial or adverse) identified during post-project benefits reviews
- B. To gain approval for the post-project activities and transferresponsibility to corporate or programme management
- C. To capture the baseline measures against which to assess benefits
- D. Checked for inclusion of activities to confirm those benefits which cannot be measured until after project closure
Answer: D
NEW QUESTION 30
Identify the missing word(s) in the following sentence. The Quality theme provides a set of rules and procedures which ensure that the [ ? ] created meet(s) the needs of the business.
- A. stages
- B. controls
- C. project management team
- D. products
Answer: D
NEW QUESTION 31
According to the 'defined roles and responsibilities' principle, what must be represented in the project management team?
- A. Directing, managing and delivering levels
- B. Project board, project manager and project assurance roles
- C. Corporate, programme management or the customer parties
- D. Business, user and supplier interests
Answer: D
Explanation:
Section: Volume B
Explanation/Reference: http://prince2.wiki/Define_roles_and_responsibilities
NEW QUESTION 32
Which is an objective of the Closing a Project process?
- A. Prepare the plan for the next stage
- B. Produce a Benefits Review Plan to identify what benefits are expected
- C. Check that all benefits are realized before closing a project
- D. Assess any benefits that have already been realized
Answer: D
NEW QUESTION 33
Identify the missing word(s) in the following sentence.
Following initiation, the Controlling a Stage process is used to manage and control each [ ? ] of a project.
- A. Team Plan
- B. benefit
- C. technical stage
- D. management stage
Answer: D
NEW QUESTION 34
Which is a benefit of applying the 'tailor to suit the project' principle?
- A. The number of outputs is reduced
- B. The capability of leadership is strengthened
- C. Project management becomes less bureaucratic
- D. The project environment complexity is reduced
Answer: D
Explanation:
Section: Volume B
NEW QUESTION 35
Which statement describes the Implement' step within the recommended risk management procedure?
- A. Identify the level of risks that can be tolerated by the project
- B. Implement the responsibilities for risks defined in the Risk Management Strategy
- C. Take planned action to respond to a risk
- D. Assess the proximity of a risk
Answer: C
NEW QUESTION 36
Which is a purpose of a quality register?
- A. To provide the status of quality activities carried out for completed products
- B. To record the date a completed work package was received
- C. To capture quality concerns about completed products
- D. To record cross-references to issues relating to the quality of the products
Answer: B
NEW QUESTION 37
Which is NOT a PRINCE2 principle?
- A. Customer/supplier environment
- B. Defined roles and responsibilities
- C. Continued business justification
- D. Learn from experience
Answer: A
NEW QUESTION 38
According to the 'defined roles and responsibilities' principle, how many categories of stakeholder interest need to be represented in the project management team?
- A. One
- B. Two
- C. Six
- D. Three
Answer: D
Explanation:
Reference: https://p2.tech-academy.co.uk/organisation/
NEW QUESTION 39
What must be produced to meet the minimum requirements when applying the change theme?
- A. Documents recording the version of each product
- B. A change budget for the analysis of change
- C. Records of the decisions made on all issues
- D. Status reports on all products being produced
Answer: C
NEW QUESTION 40
Which process provides the Project Board with the information it requires in order to commit resources to the project?
- A. Initiating a Project
- B. Managing Product Delivery
- C. Directinga Project
- D. Controlling a Stage
Answer: A
NEW QUESTION 41
Which is a purpose of a Risk Register?
- A. Capture risks that may occur during the project
- B. Record how risk management activities will be undertaken on the project
- C. Capture issues which are impacting on the delivery of the project objectives
- D. Record the risk tolerance for the project
Answer: A
Explanation:
Section: Volume B
NEW QUESTION 42
Identify the missing word in the following sentence. The [?] theme defines that the Project
Board is responsible for the overall direction and management of the project,
- A. Business Case
- B. Progress
- C. Organization
- D. Plans
Answer: C
NEW QUESTION 43
How does the use of product descriptions support the 'focus on products' principle?
- A. By documenting the delivery date for the product
- B. By documenting the quality expected by the customer
- C. By documenting the costs for the product
- D. By documenting the scope tolerance for the project
Answer: B
Explanation:
Explanation/Reference:
Reference http://prince2.wiki/Focus_on_products
NEW QUESTION 44
......
PRINCE2Foundation exam questions from Prep4pass dumps: https://questionsfree.prep4pass.com/PRINCE2Foundation_exam-braindumps.html (340 Q&As)